Course Title: Commission telecommunications network equipment

Part B: Course Detail

Teaching Period: Term1 2010

Course Code: EEET6721C

Course Title: Commission telecommunications network equipment

School: 130T Vocational Engineering

Campus: City Campus

Program: C6080 - Advanced Diploma of Telecommunications Engineering

Course Contact: Program Manager

Course Contact Phone: +61 3 9925 4468

Course Contact Email: engineering-tafe@rmit.edu.au


Name and Contact Details of All Other Relevant Staff

Kenneth Falzon

kenneth.falzon@rmit.edu.au

Nominal Hours: 150

Regardless of the mode of delivery, represent a guide to the relative teaching time and student effort required to successfully achieve a particular competency/module. This may include not only scheduled classes or workplace visits but also the amount of effort required to undertake, evaluate and complete all assessment requirements, including any non-classroom activities.

Pre-requisites and Co-requisites

None

Course Description

This course builds upon the knowledge and skills from fundamental Telecommunication Networks. The learner will further examine the emerging technologies which applicable to Australian Telecommunications and Electronic Communications systems. Learner will explore and integrate theoretical and practical knowledge to manage networks and resources for selected applications.


National Codes, Titles, Elements and Performance Criteria

National Element Code & Title:

ICTTC059C Commission telecommunications network equipment

Element:

Complete administrative tasks

Performance Criteria:

1.1 All parties associated with the commissioning are identified
1.2 Commissioning dates are established and confirmed with all parties
1.3 Commissioning parameters are established as per specification
1.4 Required resources are identified and organised
1.5 Test equipment is obtained and checked for suitability and accuracy
1.6 Customers affected by the work are informed of impending action and likely timing and impact
1.7 Frequency spectrum band is identified
1.8 Receipt of appropriate spectrum management agency licence is checked

Element:

Connect transmission bearers

Performance Criteria:

2.1 Affected systems, traffic and customers are identified
2.2 Outage duration is determined
2.3 Outage times are negotiated with appropriate groups
2.4 Existence of contingency plans is checked
2.5 Contingency plans are developed in the event that such a plan does not already exist
2.6 Emergency communications are provided if appropriate
2.7 A detailed list is prepared of both the areas impacted and the likely effect of such impact
2.8 Alarm management centre is notified of action planned
2.9 Authority to proceed is obtained from the relevant control centre
2.10 Customers affected by the outage are notified, both as to time and likely duration

Element:

Install software

Performance Criteria:

3.1 Applications programmes are installed
3.2 Hardware data is loaded as per instructions
3.3 Telephony/route and network data is loaded in accordance with predetermined instructions
3.4 Management data is loaded in accordance with specification
3.5 Billing/charging data is loaded in accordance with specification

Element:

Organise planned outages if necessary

Performance Criteria:

4.1 Distant end connection is verified with other parties
4.2 Intermediate connections are verified where required
4.3 Equipment parameters are set as per specification
4.4 Equipment is connected to the appropriate bearers
4.5 Alarms associated with the bearer and infrastructure are checked
4.6 Artificial links are installed where required and dismantled on completion of the commissioning process
4.7 Work is conducted in a manner which is safe to self, fellow workers and the public at large

Element:

Plan commissioning procedures

Performance Criteria:

5.1 Test equipment is obtained and checked for accuracy
5.2 Both end to end and section measurements are conducted in accordance with specification
5.3 Protection switching equipment is tested for operation
5.4 Order wires and auxiliary data channels are tested
5.5 Optical fibre cable connectors are cleaned as required
5.6 All specified performance tests are undertaken to ensure operation meets all prescribed parameters and specifications as detailed in the original design brief
5.7 Tests are undertaken to ensure that there is compatibility between the hardware and the software
5.8 Performance defects are corrected or brought to the attention of designers for corrective action
5.9 Test sheets are completed as per specification and test instrument usage logged as per enterprise requirements

Element:

Test equipment functionality

Performance Criteria:

6.1 Alarms are tested in conjunction with network management and operational groups
6.2 Traffic tests are simulated through the new installation
6.3 Specific equipment features installed are tested
6.4 Billing/charging arrangements are tested
6.5 Operations administration maintenance system is tested
6.6 Faults detected are diagnosed, repaired or escalated to the appropriate area when fault cannot be clearly diagnosed or repaired
6.7 Vendor related tests are initiated where required

Element:

Test hardware

Performance Criteria:

7.1 Test results are recorded as per enterprise instructions
7.2 Appropriate data bases are updated
7.3 Alarms triggered as a result of the commissioning process are rectified
7.4 Correct labelling of all equipment is checked and amendments made where required
7.5 Details of material usage is recorded and submitted to appropriate area in accordance with enterprise instructions
7.6 Job orders are completed fully and submitted to appropriate enterprise organisational unit
7.7 Design specifications are updated and returned to design area as required by enterprise requirements
7.8 Quality control procedures are followed as per enterprise policy
7.9 Installation briefs, documents and equipment manuals are handed over to operational staff in accordance with enterprise requirements
7.10 Operational staff training is undertaken where required
7.11 Transporting of tools and test equipment in suitable protective casing is organised where appropriate
7.12 All tools and test equipment are cleaned, adjusted and stored in an accessible location


Learning Outcomes



Details of Learning Activities

This is a Laboratory based course with some research and development activities.

A project is to be completed in teams of two members with a joint submission


Teaching Schedule

This is a whole year course of 36 weeks

1 Introduction to Course Outline and Assessment Criteria. Introduction to WANs
2 Introduction HDLC, X.25, Frame Relay, LCP, NCP
3 LAN Topologies - Ethenet
4 Introduction to PPP, PAP, CHAP, Encapsulation
5 Application of PAP - Exercise
6 Introduction to ISDN, TE, NT, TA
7 ISDN - Frame Relay - PVC, SVC, DLCI, CIR, Leased Line
8 Project - review of student research (10%)
9 Introduction to DSL, xDSL, ADSL, HDSL, VDSL etc.
10 Lab - configure DSL
11 Lab - configure DSL
12 Project - review of student research (10%)
13 LAN Analysis
14 TCP/IP Addressing and Routing
15 LAN Analysis Laboratory Exercise
16 Submit Project Report - Practice for the Laboratory Assessment
17 Laboratory Assessment - Demonstrate the Capability to set up a peer-to-peer Local Area Network (LAN)
18 Laboratory Assessment - Demonstrate the Capability to set up a peer-to-peer Local Area Network (LAN).
SEMESTER BREAK
19 Introduction to FibreOptics
20 Fibre Cabling
21 Optical Fibre Equipment
22 SONET - SDH
23 Practical Lab - Fibre Optics Tranmission Equiment Hardware
24 Practical Lab - FLM Provisioning
25 Practical Lab - FLM Testing
26 Practical Lab - FLM Maintenance
27 E1 and T1 transmission
28 PCM transmission
29 Intoduction to ATM
30 Application of ATM - MPLS - Generation 3/4, CoS, QoS, WIMAX, HSDPA, HSUPA
31 Cellular Systems - GSM, UMTS, EDGE
32 Satellite Links - Geo-stationary - GPS
33 Project - discussions - final arrangements
34 Submit Project Report - Practice for the Laboratory Assessment
35 Laboratory Assessment - Demonstrate the Capability to set up and operate a WAN System
36 Laboratory Assessment - Demonstrate the Capability to set up and operate a WAN System.


Learning Resources

Prescribed Texts


References


Other Resources


Overview of Assessment

The assessment is conducted in both theoretical and practical aspects of the course according to the criteria set in the National Training Package. The students are required to undertake summative assessments that bring together skills and knowledge as follows:
 Theoretical Written assessment.
 Work Simulation Projects.
 A Pass in schedule practical exercises.


Assessment Tasks

Laboratory Exercises will be conducted and assessed throughout the year.

Assignments and an On-line are required for assessment

There will be a project conducted as part of a team (pairs)


Assessment Matrix

theoretical written assessment. 40%
work simulation projects 30%
practical exercises 30%

Course Overview: Access Course Overview